Article 78 of the Saudi Government Tenders and Procurement Law

المادة 78 من نظام المنافسات والمشتريات الحكومية · الفصل الثامن: إنهاء العقود

The Article requires the final guarantee to be forfeited when a contract is terminated for reasons specified in Article 76, preserves the entity's right to compensation, and refers the decision to the Article 88 committee to consider a ban.

Official text (Arabic)

This article has not been amended since the law was issued.

يجب عند إنهاء العقد بموجب الفقرة (1) أو الفقرة (2 / أ) أو الفقرة (2 / ج) من المادة (السادسة والسبعين) من النظام، مصادرة الضمان النهائي وذلك دون إخلال بحق الجهة الحكومية في الرجوع على المتعاقد معه بالتعويض عما لحق بها من ضرر، وتزود اللجنة المنصوص عليها في المادة (الثامنة والثمانين) من النظام بنسخة من القرار؛ للنظر في منع التعامل مع المتعاقد مع الجهة الحكومية.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 78 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 78 of Government Tenders and Procurement Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Administrative Law lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Administrative Law (Board of Grievances) lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 78 of the Saudi Government Tenders and Procurement Law

When is the final guarantee forfeited in government contracts?

When the contract is terminated under paragraph (1), (2/a) or (2/c) of Article 76.

Is the guarantee forfeited if the contract is terminated because the contractor died?

This Article does not cover death; in that case Article 76 provides for settling dues and returning guarantees.

Does the entity have to settle for forfeiting the guarantee, or can it also claim compensation?

Forfeiture does not affect the entity's right to claim compensation from the contractor for the harm it suffered.

Can a contractor be banned from dealing with government entities after termination?

The Article 88 committee is given a copy of the decision to consider this, and it may impose a ban for a period not exceeding 5 years.

Articles this article refers to

More articles on Terminating a Government Contract

The texts are reproduced from the official website of the Bureau of Experts at the Council of Ministers for reference; where they differ, the officially published Arabic text prevails. This content is not legal advice.