Skip to content

Article 60 of the Saudi Government Tenders and Procurement Law

المادة 60 من نظام المنافسات والمشتريات الحكومية · الفصل الأول: صياغة العقود ومدد تنفيذها

The Article requires government entities to submit the contracts specified by the Regulations to the Ministry of Finance for review before signing; the Ministry reviews them within 15 working days or they are deemed approved.

Official text (Arabic)

This article has not been amended since the law was issued.

1- تلتزم الجهات الحكومية بعرض عقودها -التي تحددها اللائحة- على الوزارة لمراجعتها قبل توقيعها، وعلى الوزارة مراجعة تلك العقود خلال (خمسة عشر) يوم عمل من تاريخ ورودها إليها. فإن لم ترد الوزارة خلال هذه المدة عُدت موافقة. ويستثنى من حكم هذه المادة الجهات التي ليس لها اعتمادات بالميزانية العامة للدولة.

2- تحدد اللائحة ضوابط تطبيق هذه المادة.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 60 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 60 of Government Tenders and Procurement Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Administrative Law lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Administrative Law (Board of Grievances) lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 60 of the Saudi Government Tenders and Procurement Law

Must government contracts be submitted to the Ministry of Finance before signing?

Yes. The contracts the Regulations specify must be submitted to the Ministry for review before signing.

How long does the Ministry of Finance take to review a contract?

15 working days from the date the contract reaches it.

What if the Ministry does not reply within the period?

Not replying within 15 working days is deemed approval.

Are all government entities subject to this provision?

No. Entities that have no appropriations in the State's general budget are excepted.

More articles on Concluding the Government Contract and the Final Guarantee

The texts are reproduced from the official website of the Bureau of Experts at the Council of Ministers for reference; where they differ, the officially published Arabic text prevails. This content is not legal advice.