Article 59 of the Saudi Government Tenders and Procurement Law

المادة 59 من نظام المنافسات والمشتريات الحكومية · الفصل الأول: صياغة العقود ومدد تنفيذها

The contract is drawn up with the winning bidder after he is notified of the award and submits the final guarantee letter, and in public construction contracts the contractor must be enabled to start within 60 days unless the documents say otherwise.

Official text (Arabic)

This article has not been amended since the law was issued.

1- يحرر العقد بين الجهة الحكومية وصاحب العرض الفائز بعد إبلاغه بقرار الترسية وتقديم خطاب الضمان النهائي.

2- يُمكّن المتعاقد معه في عقود الإنشاءات العامة من البدء في تنفيذ العقد خلال (ستين) يوماً من تاريخ إبلاغه بقرار الترسية، مالم تنص وثائق المنافسة على غير ذلك.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 59 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 59 of Government Tenders and Procurement Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Administrative Law lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Administrative Law (Board of Grievances) lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 59 of the Saudi Government Tenders and Procurement Law

When is the contract drawn up with the winner of a government tender?

After he is notified of the award decision and submits the final guarantee letter.

Within how many days must the contractor be enabled to start performance?

Within 60 days of the date he is notified of the award decision in public construction contracts, unless the tender documents provide otherwise.

Does the 60-day period apply to all contracts?

The text specifies it for public construction contracts, and the tender documents may provide otherwise.

More articles on Concluding the Government Contract and the Final Guarantee