Article 19 of the Saudi Government Tenders and Procurement Law

المادة 19 من نظام المنافسات والمشتريات الحكومية · الفصل الثامن: شروط التعامل وتأهيل المتنافسين

The article requires the government entity to carry out pre-qualification or post-qualification, and where pre-qualification is carried out, limits the invitation to the tender to those who passed it.

Official text (Arabic)

This article has not been amended since the law was issued.

1- على الجهة الحكومية إجراء تأهيل مسبق أو لاحق في الأعمال والمشتريات وفقاً لما توضحه اللائحة.

2- في حال إجراء تأهيل مسبق، تقتصر الدعوة للمشاركة في المنافسة على من اجتاز التأهيل المسبق فقط.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 19 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 19 of Government Tenders and Procurement Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Administrative Law lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Administrative Law (Board of Grievances) lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 19 of the Saudi Government Tenders and Procurement Law

Can I take part in the tender without passing pre-qualification?

If the entity carries out pre-qualification, the invitation to take part is limited to those who passed it.

What is the difference between pre-qualification and post-qualification?

Pre-qualification takes place before bids are submitted, and post-qualification takes place after the best bid is selected and before award, under the definitions in Article 1.

Is qualification mandatory in government tenders?

Yes. The article requires the government entity to carry out pre-qualification or post-qualification as the Implementing Regulations explain.

More articles on Qualifying Bidders and Dealing Conditions

The texts are reproduced from the official website of the Bureau of Experts at the Council of Ministers for reference; where they differ, the officially published Arabic text prevails. This content is not legal advice.