Article 72 of the Saudi Government Tenders and Procurement Law
المادة 72 من نظام المنافسات والمشتريات الحكومية · الفصل السادس: الغرامات وتمديد العقود
The Article imposes on a contractor who is late a fine not exceeding 6% of the value of a supply contract and 20% of other contracts, which may be increased with the Minister's approval if announced in advance.
Official text (Arabic)
This article has not been amended since the law was issued.
إذا تأخر المتعاقد في تنفيذ العقد عن الموعد المحدد؛ تفرض عليه غرامة تأخير لا تتجاوز (6%) من قيمة عقد التوريد، ولا تتجاوز (20%) من قيمة العقود الأخرى، ويجوز زيادة تلك النسب بموافقة مسبقة من الوزير، على أن توضح تلك الزيادة للمتنافسين قبل تقديم عروضهم.
This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers
Article 72 explained in plain English
This Article sets the maximum delay fine imposed on a contractor if he is late in performing the contract past the set date.
When is it imposed? If the contractor is late in performing the contract past the date set in it.
The maximum:
- Supply contracts: the fine does not exceed 6% of the contract value.
- Other contracts (such as works and services): it does not exceed 20% of the contract value.
The text sets a ceiling the fine may not exceed, and does not state here how it is calculated day by day or in stages.
Increasing the percentages: These percentages may be increased on two conditions together:
- The prior approval of the Minister, who is the Minister of Finance.
- That the increase is explained to the bidders before they submit their bids, so they enter the tender knowing of it.
So a contractor may not be surprised after the award with a higher percentage that was not announced before bids were submitted.
After this Article comes Article 73, which regulates the fine for default in continuing service contracts at a limit not exceeding 20% of the contract value. Before it is Article 71, which makes the contractor jointly liable with the subcontractor for performance. If a contractor believes the delay is not his fault or that the fine exceeded the limit, he can consult a lawyer who specializes in government contracts and administrative cases.
Practical example
A supplier in Riyadh contracted to supply computers to a government entity for SAR 800,000, and was late in supplying past the set date. The delay fine may not exceed SAR 48,000 (6% of the supply contract value), unless a higher percentage had been approved with the Minister's prior approval and announced to the bidders before bids were submitted.
Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.
How we write and review contentA question about Article 72 of Government Tenders and Procurement Law?
Describe what happened and specialist lawyers answer. You can write in English.
- Completely free
- Lawyers from the directory answer
- Your name stays hidden
Administrative Law lawyers: ask a specialist about your case
Describe your situation briefly and we'll suggest a lawyer who specialises in this law
Administrative Law (Board of Grievances) lawyers
Lawyers who handle this kind of case
Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company
Active contributorUnwan Law Firm
Frequently asked questions about Article 72 of the Saudi Government Tenders and Procurement Law
What is the delay fine percentage in government supply contracts?
It does not exceed 6% of the supply contract value.
What is the maximum delay fine in contracting and other contracts?
It does not exceed 20% of the contract value.
May the delay fine percentage be increased?
Yes, with the prior approval of the Minister of Finance, provided the increase is explained to the bidders before they submit their bids.
More articles on Delay Penalty and Contract Extension
- Article 73
The Article imposes on a contractor who defaults in continuing service contracts a fine not exceeding 20% of the contract value, with deduction of the value of the work not performed.
إذا قصّر المتعاقد معه في عقود الخدمات ذات التنفيذ المستمر في تنفيذ التزاماته؛ تُفرض عليه غرامة لا تتجاوز (20%) من قيمة العقد، مع حسم قيمة الأعمال التي لم تُنفذ،
- Article 74
The Article sets five cases in which a government contract is extended and the contractor is exempted from the fine, and refers the rules and procedures for extension and exemption to the Regulations.
يكون تمديد العقد والإعفاء من الغرامة في الحالات الآتية: 1- إذا كُلف المتعاقد معه بأعمال إضافية، بشرط أن تكون المدة المضافة متناسبة مع حجم الأعمال وطبيعتها وتاري
- Article 75
The Article allows the government entity to withdraw part of the works and purchases and carry them out at the contractor's expense if he breaches his contractual obligations after being warned.
للجهة الحكومية سحب جزء من الأعمال والمشتريات وتنفيذها على حساب المتعاقد معه؛ إذا أخل بالتزاماته التعاقدية بعد إنذاره، وتوضح اللائحة ما يلزم لتطبيق هذه المادة.
The texts are reproduced from the official website of the Bureau of Experts at the Council of Ministers for reference; where they differ, the officially published Arabic text prevails. This content is not legal advice.