Article 72 of the Saudi Government Tenders and Procurement Law

المادة 72 من نظام المنافسات والمشتريات الحكومية · الفصل السادس: الغرامات وتمديد العقود

The Article imposes on a contractor who is late a fine not exceeding 6% of the value of a supply contract and 20% of other contracts, which may be increased with the Minister's approval if announced in advance.

Official text (Arabic)

This article has not been amended since the law was issued.

إذا تأخر المتعاقد في تنفيذ العقد عن الموعد المحدد؛ تفرض عليه غرامة تأخير لا تتجاوز (6%) من قيمة عقد التوريد، ولا تتجاوز (20%) من قيمة العقود الأخرى، ويجوز زيادة تلك النسب بموافقة مسبقة من الوزير، على أن توضح تلك الزيادة للمتنافسين قبل تقديم عروضهم.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 72 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 72 of Government Tenders and Procurement Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Administrative Law lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Administrative Law (Board of Grievances) lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 72 of the Saudi Government Tenders and Procurement Law

What is the delay fine percentage in government supply contracts?

It does not exceed 6% of the supply contract value.

What is the maximum delay fine in contracting and other contracts?

It does not exceed 20% of the contract value.

May the delay fine percentage be increased?

Yes, with the prior approval of the Minister of Finance, provided the increase is explained to the bidders before they submit their bids.

More articles on Delay Penalty and Contract Extension

The texts are reproduced from the official website of the Bureau of Experts at the Council of Ministers for reference; where they differ, the officially published Arabic text prevails. This content is not legal advice.