Article 38 of the Saudi Civil Transactions Law

المادة 38 من نظام المعاملات المدنية · الفرع الأول: أركان العقد أولًا: الرضى

A contract between parties present, including by direct means of communication, is concluded at the time and place the acceptance is issued, and between parties not present when the offeror learns of the acceptance, unless otherwise agreed.

Official text (Arabic)

This article has not been amended since the law was issued.

1- إذا كان المتعاقدان حاضرين في مكانٍ واحدٍ أو في مكانين مختلفين عبر وسائل الاتصال المباشرة؛ عُدَّ العقد قد تمَّ في الزمان والمكان اللذين صدر فيهما القبول؛ ما لم يُتفق على خلاف ذلك.

2- إذا كان المتعاقدان غائبين؛ عُدَّ العقد قد تمَّ في الزمان والمكان اللذين علم فيهما الموجب بالقبول؛ ما لم يُتفق على خلاف ذلك.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 38 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 38 of Civil Transactions Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Civil Litigation & Compensation lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Civil Litigation & Compensation lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 38 of the Saudi Civil Transactions Law

When is a contract concluded if the parties are in different cities?

If they communicate by direct means of communication, the contract is concluded at the time and place the acceptance is issued. If they are not present together, it is concluded at the time and place the offeror learns of the acceptance, unless otherwise agreed.

When is a contract concluded between parties who are not present?

At the time and place at which the offeror learned of the acceptance, unless otherwise agreed.

Can the parties agree on a different time or place for the contract to be concluded?

Yes. The rule in both cases applies unless the contracting parties agree otherwise.