Article 70 of the Saudi Government Tenders and Procurement Law

المادة 70 من نظام المنافسات والمشتريات الحكومية · الفصل الخامس: التنازل عن العقد والتعاقد من الباطن

The Article bars the contractor from assigning the government contract or part of it to another contractor, undertaker or supplier without written approval from the government entity and the Ministry of Finance.

Official text (Arabic)

This article has not been amended since the law was issued.

لا يجوز للمتعاقد معه التنازل عن العقد أو جزء منه لمقاول أو متعهد أو مورّد آخر إلا بعد الحصول على موافقة مكتوبة من الجهة الحكومية والوزارة، وتوضح اللائحة شروط وضوابط التنازل عن العقد أو جزء منه.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 70 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 70 of Government Tenders and Procurement Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Administrative Law lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Administrative Law (Board of Grievances) lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 70 of the Saudi Government Tenders and Procurement Law

May a government contract be assigned to another company?

Only after obtaining written approval from the government entity and the Ministry of Finance.

Is the government entity's approval alone enough for assignment?

No. The text requires written approval from the government entity and the Ministry together.

Does the ban cover assigning part of the contract?

Yes. The ban covers assigning the contract or part of it.

More articles on Assignment and Subcontracting

The texts are reproduced from the official website of the Bureau of Experts at the Council of Ministers for reference; where they differ, the officially published Arabic text prevails. This content is not legal advice.