Article 9 of the Saudi Building Code Law
المادة 9 من نظام تطبيق كود البناء السعودي
This article bars occupying a building without an occupancy certificate according to the occupancy classification in the Code and under the procedures and periods in the regulations, and makes the certificate an essential condition for the full release of electric current.
Official text after amendments (Arabic)
Compiled from the original text and every officially published amendment; the amendments are shown in full below for comparison.
لا يجوز إشغال البناء إلا بموجب شهادة إشغال بحسب تصنيف الإشغال الوارد في الكود، ووفقاً للإجراءات والمدد التي تحددها اللوائح، وتعد شهادة الإشغال شرطاً أساسياً للإطلاق الكلي للتيار الكهربائي
This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers
Article 9 explained in plain English
This article sets a clear rule: a building may not be occupied except under an occupancy certificate. Under Article 1, an occupancy certificate is permission to occupy the building, issued by the municipal body (the amanah or municipality) after confirming that it complies with the Code.
The article contains the following elements:
- The basis: the certificate is issued according to the occupancy classification in the Code, that is, according to the type of use of the building as the Code classifies it.
- Procedures and periods: the regulations set them; the Law does not state them.
- Electricity: the occupancy certificate is an essential condition for the full release of electric current.
According to the record of amendments, a phrase providing that the occupancy certificate is an essential condition for connecting services was earlier removed from the article, and the wording on the full release of electric current was then added by Royal Decree No. M/88 dated 10/4/1446 AH. The text in force therefore speaks specifically of the full release of electricity and does not address other services.
In practice, an owner should not live in, rent out or use the building before obtaining the occupancy certificate, and the full release of electric current depends on it. The building's compliance with the Code is connected with the designer's, contractor's and supervisor's obligation to follow the Code under Article 8. Where there is difficulty in obtaining the certificate, a lawyer specializing in administrative and real estate matters can be consulted.
Practical example
Nasser finished building a residential building in Riyadh and wants to rent out its apartments. Before that he must obtain an occupancy certificate from the municipality according to the occupancy classification in the Code, because the building may not be occupied without it, and the full release of electric current is also conditional on it.
Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.
How we write and review contentAdministrative Law lawyers: ask a specialist about your case
Describe your situation briefly and we'll suggest a lawyer who specialises in this law
Administrative Law (Board of Grievances) lawyers
Lawyers who handle this kind of case
Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company
Al-Safwa Law Office and Legal Consultancy
Frequently asked questions about Article 9 of the Saudi Building Code Law
Can I live in a building without an occupancy certificate?
No. The article provides that a building may not be occupied except under an occupancy certificate.
Is an occupancy certificate a condition for connecting electricity?
The occupancy certificate is an essential condition for the full release of electric current.
Who issues the occupancy certificate?
The municipal body (the amanah or municipality) issues it after confirming that the building complies with the Code.
What are the procedures and time for issuing an occupancy certificate?
The Law does not set them. The article refers to the procedures and periods that the regulations set.
Amendment history
Amendment
Official amendment text (Arabic)
حذف عبارة "وتعد شهادة الإشغال شرطاً أساساً لإيصال الخدمات" لتصبح بالنص الآتي: "لا يجوز إشغال البناء إلا بموجب شهادة إشغال بحسب تصنيف الإشغال الوارد في الكود، وفقاً للإجراءات والمدد التي تحددها اللوائح".
Royal Decree No. M/88 — 10/4/1446 AH
Official amendment text (Arabic)
- عُدلت هذه المادة وذلك بموجب المرسوم الملكي رقم (م/88) وتاريخ 1446/4/10هـ، وذلك بإضافة عبارة "وتعد شهادة الإشغال شرطاً أساسياً للإطلاق الكلي للتيار الكهربائي" إلى عجز المادة لتصبح بالنص الآتي:
" لا يجوز إشغال البناء إلا بموجب شهادة إشغال بحسب تصنيف الإشغال الوارد في الكود، ووفقاً للإجراءات والمدد التي تحددها اللوائح، وتعد شهادة الإشغال شرطاً أساسياً للإطلاق الكلي للتيار الكهربائي".
Original text before the amendments (Arabic)
لا يجوز إشغال البناء إلَّا بموجب شهادة إشغال بحسب تصنيف الإشغال الوارد في الكود، ووفقاً للإجراءات والمدد التي تحددها اللوائح، وتعد شهادة الإشغال شرطاً أساساً لإيصال الخدمات.