Article 477 of the Saudi Civil Transactions Law

المادة 477 من نظام المعاملات المدنية · الفرع الخامس: انتهاء عقد المقاولة

The article provides that a contractor who started performance and then was unable to complete it for a reason beyond the contractor's control is entitled to the value of what was done and what was spent on the rest to the extent of its benefit to the client.

Official text (Arabic)

This article has not been amended since the law was issued.

إذا بدأ المقاول في التنفيذ ثم أصبح عاجزًا عن إتمامه لسبب لا يد له فيه؛ فإنه يستحق قيمة ما تم من الأعمال، وما أنفق في العمل الذي لم يتم بقدر ما عاد على صاحب العمل من نفع.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 477 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 477 of Civil Transactions Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Civil Litigation & Compensation lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Civil Litigation & Compensation lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 477 of the Saudi Civil Transactions Law

What is a contractor entitled to if unable to finish the work for a reason beyond the contractor's control?

The contractor is entitled to the value of the work done, and what was spent on the unfinished work to the extent of the benefit to the client.

Does the contractor recover everything spent on the unfinished part?

No, only to the extent of the benefit to the client.

Does this article apply if the inability is due to the contractor?

The article requires that the inability be for a reason beyond the contractor's control.

More articles on Contracting (Construction) Contract

The texts are reproduced from the official website of the Bureau of Experts at the Council of Ministers for reference; where they differ, the officially published Arabic text prevails. This content is not legal advice.