The article requires the client to promptly take delivery of the work once completed; if the client refuses without a lawful reason despite being notified, and it is lost or damaged without the contractor's wrongdoing or default, the contractor owes no compensation.

Official text (Arabic)

This article has not been amended since the law was issued.

إذا أتم المقاول العمل ووضعه تحت تصرف صاحب العمل لزمته المبادرة إلى تسلمه، فإن امتنع بغير سبب مشروع رغم إعلامه بذلك وهلك في يد المقاول أو تلف دون تعديه أو تقصيره؛ لم يلزم المقاول التعويض.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 468 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

A question about Article 468 of Civil Transactions Law?

Describe what happened and specialist lawyers answer. You can write in English.

  • Completely free
  • Lawyers from the directory answer
  • Your name stays hidden
Ask a lawyer for free

Civil Litigation & Compensation lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Civil Litigation & Compensation lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Active contributor
Riyadh Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Unwan Law Firm

Riyadh
Labour & Employment LawAdministrative LawCivil Litigation & CompensationCommercial & Corporate Law+3
See all lawyers

Frequently asked questions about Article 468 of the Saudi Civil Transactions Law

Must the client take delivery of the work as soon as it is finished?

If the contractor completes the work and places it at the client's disposal, the client must promptly take delivery of it.

Is the contractor liable for damage to the work if the client refused to take it?

The contractor owes no compensation if the client refused without a lawful reason despite being notified, and the work was lost or damaged without the contractor's wrongdoing or default.

What if the damage was caused by the contractor's default?

The rule that no compensation is owed is conditional on the loss or damage occurring without the contractor's wrongdoing or default.