Article 22 of the Saudi Privatization Law
المادة 22 من نظام التخصيص
This article lets the competent authority extend or renew a partnership contract in cases of delay due to circumstances beyond control, suspension of the project, recovery of additional costs, or changes to specifications in the public interest.
Official text (Arabic)
This article has not been amended since the law was issued.
للجهة المختصة الموافقة على تمديد عقد الشراكة بين القطاعين العام والخاص أو تجديده، في أي من الحالات الآتية:
1- تأخر إنجاز مشروع التخصيص أو انقطاع تشغيله بسبب ظروف لا دخل للأطراف فيها وخارجة عن سيطرتهم.
2- تعليق مشروع التخصيص.
3- السماح للطرف الخاص باسترداد التكاليف الإضافية الناشئة عن الاشتراطات الإضافية التي ليس من المتوقع أن يكون قادرًا على استردادها خلال المدة الأصلية للعقد.
4- تعديل بعض مواصفات العقد، أو العقد التابع؛ وفقًا لمقتضيات المصلحة العامة، وذلك بعد الحصول على الموافقات اللازمة لهذا التعديل؛ وفقًا لما يقضي به النظام.
This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers
Article 22 explained in plain English
This article sets out four cases in which the competent authority may approve extending or renewing a partnership contract:
- Circumstances beyond control: delay in completing the project or interruption of its operation due to circumstances the parties had no part in and that are beyond their control.
- Suspension: suspension of the privatization project, which Article 21 allows in the public interest.
- Additional costs: allowing the private party to recover additional costs arising from additional requirements, where it was not expected to recover them during the original term of the contract.
- Changes to specifications: amending some specifications of the contract or the subsidiary contract as the public interest requires, after obtaining the approvals needed for the change under the Law.
The logic is fairness: if the private party loses part of the contract term, or bears unforeseen costs through no fault of its own, an extension restores its opportunity to achieve the expected return.
The wording "the competent authority may approve" means that extension is a discretionary power, not an automatic right. Anyone wishing to request an extension should consult a lawyer who specializes in commercial matters and partnership contracts.
Practical example
The operation of a desalination plant run by a company under a partnership arrangement was delayed for a full year because of circumstances beyond the control of both parties. The competent authority may approve extending the contract to compensate the company for this period.
Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.
How we write and review contentAdministrative Law lawyers: ask a specialist about your case
Describe your situation briefly and we'll suggest a lawyer who specialises in this law
Administrative Law (Board of Grievances) lawyers
Lawyers who handle this kind of case
Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company
Al-Safwa Law Office and Legal Consultancy
Frequently asked questions about Article 22 of the Saudi Privatization Law
When can a partnership contract with the government be extended?
In case of delay or interruption due to circumstances beyond the parties' control, suspension of the project, recovery of additional costs, or changes to specifications in the public interest.
Is an extension a right of the private party?
No. The text gives the competent authority the power to approve an extension in these cases.
More articles on Duration and Extension of a Partnership Contract