Article 11 of the Saudi Privatization Law

المادة 11 من نظام التخصيص

Where a license or permit needed for a privatization project cannot be issued or is delayed by the competent government entity, the Council of Economic and Development Affairs issues its direction to it on the basis of a report prepared by the executing entity.

Official text (Arabic)

This article has not been amended since the law was issued.

دون الإخلال بأحكام العقد المتعلقة بتوزيع المخاطر بين أطراف العقد، عند تعذر إصدار رخصة، أو ترخيص، أو تصريح لازم لأي مشروع تخصيص، أو تأخر إصداره من قبل الجهة الحكومية المعنية نظامًا بإصداره، يُصدر المجلس توجيهه لها بما يراه مناسبًا، بناءً على تقرير تُعده الجهة التنفيذية بالتنسيق مع الجهة الحكومية المعنية؛ متضمنًا وصفًا للحالة، وأسباب التعذر أو التأخر في الإصدار، والتكاليف الناجمة عن ذلك والحلول المقترحة.

This is the official Arabic wording, the only legally binding version. We do not translate the law itself; the explanation below is ours. Official source: Bureau of Experts at the Council of Ministers

Article 11 explained in plain English

Practical example

Translated from our Arabic explanation with machine assistance. For guidance only; it does not replace advice from a lawyer on your situation.

How we write and review content

Administrative Law lawyers: ask a specialist about your case

Describe your situation briefly and we'll suggest a lawyer who specialises in this law

Administrative Law (Board of Grievances) lawyers

Lawyers who handle this kind of case

Dr. Ali Al-Rubaie Law Office and Ittihad Al-Asr Legal Company

Riyadh — العليا Consultation from SAR 450
Labour & Employment LawCriminal LawAdministrative LawCivil Litigation & Compensation+4

Al-Safwa Law Office and Legal Consultancy

Jeddah 3.3 (1)
Criminal LawAdministrative LawCommercial & Corporate LawFamily & Personal Status Law+1
See all lawyers

Frequently asked questions about Article 11 of the Saudi Privatization Law

What happens if a license needed for a privatization project is delayed?

The Council of Economic and Development Affairs issues its direction to the entity concerned on the basis of a report prepared by the executing entity.

What does the delayed-license report contain?

A description of the situation, the reasons for the inability or delay, the resulting costs, and the proposed solutions.

Does the Council's intervention change the allocation of risks in the contract?

No. The article applies without prejudice to the contract's provisions on the allocation of risks.

More articles on Authorities Responsible for Privatization Projects

The texts are reproduced from the official website of the Bureau of Experts at the Council of Ministers for reference; where they differ, the officially published Arabic text prevails. This content is not legal advice.